KL ECO CITY - Parcel B (Podium)

KL ECO CITY SDN BHD

 

Contract A

 

Location: Jalan Bangsar, KL

Date of Commencement : 7 Apr 2014

Date of Completion :

   (1) Section 1

     (i) Original Date of Completion : 6 Jan 2016

     (ii) Revised Date of Completion (EOT Granted) :

          30 Mar 2016

     (iii) Actual CPC : 15 Febuary 2016
           [Completed 45 days ahead of schedule]

   (2) Overall

     (i) Original Date of Completion : 6 March 2017

     (ii) Revised Date of Completion (EOT Granted) :

          26 Jun 2017

     (iii) Actual CPC : 17 May 2017

           [Completed 40 days ahead of schedule]